Digging has begun

We have broken ground on the 8th Living Building Challenge project in BC.  The ground was easy and sandy.  Ground water was found about 8’ below the surface.  This was expected due to the spring rains and high water tables of the nearby creek.  Our rain water tanks and earth tubes will be kept 1’ above ground water.  Our foundation and footings are well above this level (2’ required by local code).

 